Calibre Estate - Bio-Retention Basin

Construction of Bio Retention Basin

Project Description

Construction of Bio Retention Basin

  • Clearing and grubbing batter and trench line
  • Excavation of Bio Retention Basin.
  • Pond base preparation and removal of unsuitable materials
  • Cut and Backfill HDPE anchor trench
  • Supply and installation of 1.5mm HDPE Membrane
  • Mechanically fix liner to sand stone wall
  • Installation of pipework and pits
  • Connection to existing Bio Retention Basin
  • Supply and Installation of bio retention media as per drawings and specification.